Budimex Passes Halfway Point Ornowo-Wirwajdy Expressway Construction

On September 16, 2021, Budimex announced that it had passed the halfway point in the construction of Ornowo-Wirwajdy section of the S5 expressway.

According to the company, the section under contract is 5.3 km long and represents a part of the S5 expressway to Grudziadz and, ultimately, to Bydgoszcz, Poznan, and Wroclaw.

“The implementation of the investment is being carried out in the ‘Design and Build’ formula,” noted Budimex Infrastructure Construction Director Cezary Lysenko. “Currently, after 16 months of construction works, the Ornowo -Wirwajdy expressway section is at the stage of over 50% advancement. Given that the completion of the contract is scheduled for May 2023, this represents very good progress of the construction works.”

Lysenko added that “Work is being carried out on many fronts simultaneously. The construction of embankments, bridge structures and roadway construction layers is underway. The first sections of bituminous substructures have already been laid. On average, 170 workers and 98 heavy equipment units are employed on the construction site.”

 

Get the memo – every week

Essential real estate market updates, straight to your inbox.

Urban Partners Refinances Co-Living Portfolio in Gdansk with Santander Bank Polska

The financing is for three co-living projects: Noli Gdansk Wrzeszcz, Noli Gdansk Riverside, and Noli Gdansk Old Town – developed under the NSF V fund.

Jakub Kutzmann Joins Baker Tilly Legal Poland as Head of Real Estate

Before joining the firm, he worked for Tomczykowski Tomczykowska as a Partner from 2024 to 2026 and for White & Case as a Local Partner from 2020 to 2023.

Accolade Secures EUR 42 Million Financing for Park Szczecin Trzebusz

According to the company, as part of the first phase of the investment, more than 25,500 square meters of modern industrial space is being delivered.